Hydreco Hydraulics
Regents Park, Western Sydney NSW

Office and warehouse fitout project delivered by DY Constructions for Hydreco Hydraulics

Project Details

Location

Regents Park, Western Sydney NSW

Industry

Wellness and Fitness Services

Size

xxxm2

Value

$210k

Designer

DY Constructions Australia

Duration

xxx weeks

Delivery Method

Lump Sum

  • New plasterboard partitions and acoustic insulation
  • Epoxy coating to workshop floor
  • Split system installed for server room
  • Vinyl flooring to kitchen and boardroom
  • Mechanical louvre and air balancing works
  • Fire protection adjustments and signage
  • Privacy film to glazing and repaint throughout

Project overview

Office and warehouse fitout completed for Hydreco Hydraulics in Regents Park, featuring enclosed offices, bathroom upgrades, and improved ventilation.

Client Brief

ProGroup Management engaged DY Constructions Australia to elevate the quality and functionality of their office environment and accommodate a growing team. The client sought a modern, well-planned fitout that would maximise workspace efficiency while enhancing overall presentation.

DY delivered a full-scope solution across two levels, including new office partitions, custom joinery, acoustic upgrades, flooring, furniture, lighting, and services. The works were tailored to support both day-to-day operations and future expansion.

Challenges

The client initially provided a floorplan that did not meet BCA and accessibility requirements, requiring DY to redesign the layout to ensure full compliance. As part of the brief to expand the office, the client also requested that the workspace extend into the existing warehouse—a complex adjustment that required careful consideration of mechanical systems and building code constraints.

Additionally, the client aimed to maximise workstation capacity within a limited footprint. DY had to carefully plan and adjust workstation placement to achieve optimal density without compromising usability or compliance, accommodating several design changes throughout the process.

The Solution

DY collaborated closely with a private certifier to review the client’s initial drawings, making iterative adjustments until the layout achieved full compliance and met the client’s functional needs. This ensured the final plan was both regulation-compliant and aligned with the intended use of the space.

For the office extension into the warehouse, DY coordinated layout modifications and installed a new air conditioning system to service the expanded area, ensuring the build met mechanical and BCA requirements. To address space constraints, DY carefully planned the workstation layout to maximise capacity without compromising movement, comfort, or compliance—successfully delivering a design that met the brief.

The Result

The project was completed to the client’s satisfaction, with DY securing the Occupation Certificate in time for ProGroup Management’s planned move-in. The final scope included full office partitioning, custom joinery, acoustic panels, flooring, lighting, electrical and data works, workstation installation, and new air conditioning for the expanded office area—delivered as a complete, compliant fitout solution.

Get In Touch

Please Submit Your Enquiry and our friendly staff will contact you to arrange a free consultation at your premises to discuss your project in detail.

Scope of Works

  • Partition Works – Installation of new full-height plasterboard partitions with acoustic insulation and solid-core doors.
  • Flooring – Epoxy coating to workshop area and new vinyl flooring to kitchen and boardroom.
  • Mechanical Services – Supply and install of new split system to server room and mechanical louvre with fresh air fan.
  • Fire & Compliance – Installation of extinguishers, fire signage, and coordination of fire protection adjustments.
  • Additional Works – Application of privacy film to glazing, patch and repaint of ceilings and walls, and coordination of all required compliance documentation.