Piksters
Frenchs Forest, Northern Beaches, NSW

Office fitout project delivered by DY Constructions for Piksters

Project Details

Location

Frenchs Forest, Northern Beaches, NSW

Industry

Dental and Healthcare

Size

180m2

Value

$135k

Designer

DY Constructions Australia

Duration

xxx weeks

Delivery Method

Lump Sum

  • Office fitout including five enclosed offices
  • Full-height plasterboard and glass partitions
  • Aluminium-framed doors and hardware
  • Mechanical adjustments for new layout
  • Power and data upgrades throughout
  • Patch painting to new partitions
  • Floor protection and site establishment
  • Coordination with client-nominated contractors
  • Works completed in a live environment

Project overview

Refurbishment and Office Upgrade for Healthcare Supplier Piksters, Featuring New Partitioned Offices, Boardroom AV Prep, and Coordinated Services Integration at Frenchs Forest HQ.

Client Brief

Piksters (Erskine Oral Care) engaged DY Constructions Australia to carry out a small-scale office refurbishment at their Frenchs Forest premises. The client required new office partitioning, feature finishes, and reconfiguration of the existing layout to better suit future workspace needs. The works also included minor acoustic upgrades and compliance considerations, all delivered with minimal disruption to the occupied environment.

Challenges

While the project was not complex, works had to be carried out in a live operational setting, requiring dust control and protection of existing finishes. Coordination of access, deliveries, and sequencing also required attention to avoid disruption to the client’s team.

The Solution

DY implemented containment barriers, used floor and lift protection, and staged deliveries to limit impact. Our team coordinated efficiently with building management and the client to ensure the works progressed smoothly and safely.

The Result

The project was completed on time and to scope, providing the client with a refreshed and functional workplace aligned with their operational needs. The client was pleased with the final result and the care taken during construction in the live environment.

Get In Touch

Please Submit Your Enquiry and our friendly staff will contact you to arrange a free consultation at your premises to discuss your project in detail.

Scope of Works

  • Partition Installation – Supply and installation of new full-height plasterboard partitions and aluminium-framed glass walls to form five private offices and a showroom/conference room, with all glazing and openings meeting accessibility and BCA standards.

  • Doors & Hardware – Installation of custom solid-core doors with compliant lever hardware and single-action escape functionality.

  • Mechanical & Electrical Works – Adjustment of the existing mechanical system to suit new office layout, including relocation of diffusers. Power and data outlets supplied and installed as per workstation layout, including relocation of existing GPOs and light switches.

  • Painting – Patch painting to all new wall and ceiling junctions affected by fitout works.

  • Site Preparation & Protection – Floor protection, site establishment, and safety compliance measures implemented throughout the works.

  • Coordination – Integration and coordination with client-nominated trades for supplementary works including furniture and tech installations.

  • Final Clean & Handover – Waste removal, progress cleaning, and final detailing prior to handover.