Project Details
Location
Sydney CBD, NSW
Industry
Healthcare
Size
1100m2
Value
$230k
Designer
DY Constructions Australia
Duration
2 weeks
Delivery Method
Lump Sum
Completion
2024
- Full carpet replacement across Levels 5 and 6
- Repainting of all walls, ceilings, and doors
- Minor patching and surface preparation
- Floor protection and WHS management
- Progress and final trade cleaning
- Additional patching and painting as part of minor works
- Waste removal and site handover
- Works delivered in a live office environment
Project overview
Office Refurbishment and Maintenance for ACSQHC’s Sydney CBD Headquarters.
Client Brief
The Australian Commission on Safety and Quality in Health Care (ACSQHC) engaged DY Constructions Australia to modernise their Sydney CBD office across two floors. The client sought to refresh the workspace through a full repaint of all walls, ceilings, and doors, along with a major carpet tile replacement to improve the overall look and feel of the environment.
Challenges
The project required completion within a short timeframe to minimise disruption and avoid extended office closure. This placed pressure on scheduling and coordination to ensure works were delivered quickly without compromising quality.
The client also requested thorough approval of carpet tile selection and paint colours prior to commencement, requiring DY to work closely with them to finalise the perfect finishes. Additionally, with existing office furniture remaining in place during parts of the works, extra care was taken to protect all items and avoid any damage throughout the refurbishment.
The Solution
DY staged the works by splitting the office into sections, allowing staff to maintain access to parts of the workplace while refurbishment progressed. This approach minimised disruption and ensured the project stayed on schedule.
To meet the client’s expectations on finishes, DY provided carpet and paint samples, testing colours on site to achieve the perfect match with the existing environment. Throughout the works, the site manager closely coordinated trades to maintain smooth progress, while existing furniture was carefully covered and protected to prevent any damage.
The Result
The project was delivered on time and within budget, with the client expressing high satisfaction with the outcome. DY completed the full repainting of walls, ceilings, and doors, along with the replacement of carpet tiles across two floors, refreshing the entire office space. The positive feedback was reinforced by a written testimonial commending DY’s professionalism and quality of work.