Australian Commission on Safety and Quality in Health Care (ACSQHC)
Sydney CBD, NSW

Office refurbishment project delivered by DY Constructions for ACSQHC

Project Details

Location

Sydney CBD, NSW

Industry

Healthcare

Size

1100m2

Value

$230k

Designer

DY Constructions Australia

Duration

2 weeks

Delivery Method

Lump Sum

  • Full carpet replacement across Levels 5 and 6
  • Repainting of all walls, ceilings, and doors
  • Minor patching and surface preparation
  • Floor protection and WHS management
  • Progress and final trade cleaning
  • Additional patching and painting as part of minor works
  • Waste removal and site handover
  • Works delivered in a live office environment

Project overview

Office Refurbishment and Maintenance for ACSQHC’s Sydney CBD Headquarters.

Client Brief

The Australian Commission on Safety and Quality in Health Care (ACSQHC) engaged DY Constructions Australia to modernise their Sydney CBD office across two floors. The client sought to refresh the workspace through a full repaint of all walls, ceilings, and doors, along with a major carpet tile replacement to improve the overall look and feel of the environment.

Challenges

The project required completion within a short timeframe to minimise disruption and avoid extended office closure. This placed pressure on scheduling and coordination to ensure works were delivered quickly without compromising quality.

The client also requested thorough approval of carpet tile selection and paint colours prior to commencement, requiring DY to work closely with them to finalise the perfect finishes. Additionally, with existing office furniture remaining in place during parts of the works, extra care was taken to protect all items and avoid any damage throughout the refurbishment.

The Solution

DY staged the works by splitting the office into sections, allowing staff to maintain access to parts of the workplace while refurbishment progressed. This approach minimised disruption and ensured the project stayed on schedule.

To meet the client’s expectations on finishes, DY provided carpet and paint samples, testing colours on site to achieve the perfect match with the existing environment. Throughout the works, the site manager closely coordinated trades to maintain smooth progress, while existing furniture was carefully covered and protected to prevent any damage.

The Result

The project was delivered on time and within budget, with the client expressing high satisfaction with the outcome. DY completed the full repainting of walls, ceilings, and doors, along with the replacement of carpet tiles across two floors, refreshing the entire office space. The positive feedback was reinforced by a written testimonial commending DY’s professionalism and quality of work.

Client Testimonial

I am pleased to provide a reference for DY Construction, who recently completed an office refurbishment project for us, including new carpet installation and repainting in a CBD building across two floors.

Throughout the project, DY Construction demonstrated a high level of professionalism and attention to detail. Their team, especially Mark Savelyev, was personable, easy to work with, and maintained excellent communication at every stage. They coordinated trades seamlessly, ensuring minimal disruption to our operations and keeping everything on track.

One of the standout aspects of their service was their commitment to timelines. The project was completed within the agreed schedule, with no unnecessary delays. They also conducted thorough pre- and post-project checks, ensuring quality workmanship and addressing any minor issues proactively.

Overall, we were highly satisfied with their work and would not hesitate to engage them again for future projects. I highly recommend DY Construction to anyone seeking a reliable and professional construction team.

Regards,

Alexandra Sonsie
Director, HR

Get In Touch

Please Submit Your Enquiry and our friendly staff will contact you to arrange a free consultation at your premises to discuss your project in detail.

Scope of Works

  • Carpet Replacement – Removal of existing carpet tiles and installation of new commercial-grade tiles (Inspired Floors “Mist” range) across Level 5 and part of Level 6, including furniture relocation and trims where required.
  • Painting & Surface Preparation – Preparation and repainting of all existing painted surfaces, including walls, ceilings, and thirty-two internal doors. Minor patching of holes and imperfections prior to painting.
  • Minor Works – Additional patching and repainting to columns and areas with wall fixings removed, completed under a separate variation.
  • Site Preparation & Protection – Installation of heavy-duty plastic floor protection, adherence to WHS requirements, and site safety management throughout works.
  • Cleaning & Waste Removal – Daily and final trade cleaning, vacuuming, and removal of all waste materials.
  • Project Management – Full coordination of trades, scheduling of works to minimise disruption, and quality control inspections at all stages.