Guildford Public School
Guildford, Western Sydney, NSW

Educational fitout delivered by DY Constructions for Guildford Public School

Project Details

Location

Guildford, Western Sydney, NSW

Industry

Education - Primary

Size

70m2

Value

$100k

Designer

DY Constructions Australia

Duration

4 weeks

Delivery Method

Lump Sum

  • Educational office and meeting room fitout
  • New solid and glazed partition walls
  • Set plasterboard ceilings
  • Custom MDF door installations
  • Electrical and data fitout
  • Floor protection and rubbish removal
  • Painting of partitions, ceilings, and doors
  • Optional acoustic pinboards and privacy film
  • Compliant glazing and hardware
  • Completed in an active school environment

Project overview

Office and Meeting Room Fitout at Guildford Public School, Western Sydney.

Client Brief

Guildford Public School engaged DY Constructions Australia to renovate and refurbish an existing staff office space, timed to align with the end-of-year school holidays. The objective was to improve the functionality and layout of the space ahead of the new school term.

DY was responsible for scoping and delivering the full fitout, which included new solid and glazed partitions, custom doors, plasterboard ceilings, electrical and data installations, painting, and final detailing. The works were coordinated closely with the school to ensure all needs were met within the limited project window.

Challenges

The project was delivered during the end-of-year school holidays, one of the busiest periods for DY, requiring tight scheduling to complete works before staff returned. With limited access to school personnel during the break, all project details and approvals had to be finalised upfront to avoid delays or rework.

DY also had to ensure all works complied with the EFSG (Educational Facilities Standards and Guidelines) issued by School Infrastructure NSW, which added additional requirements around layout, accessibility, and compliance.

The Solution

To meet the strict holiday timeframe, DY carefully planned and coordinated the works, supported by strong project management and a reliable network of skilled subcontractors. All design details and approvals were gathered before the school holidays to minimise disruption and ensure a smooth, uninterrupted delivery.

DY also ensured full compliance with the EFSG by reviewing all layout and construction requirements in advance, applying them throughout the fitout to meet School Infrastructure NSW standards.

The Result

The project was completed on time and within budget, ready for staff to return at the start of the new school term. The school was pleased with the high-quality outcome and the improved functionality of the space. The scope included new office partitions, ceilings, doors, power and data installations, and final painting—delivered with minimal disruption and in full compliance with educational standards.

Get In Touch

Please Submit Your Enquiry and our friendly staff will contact you to arrange a free consultation at your premises to discuss your project in detail.

Scope of Works

  • Site Preparation – Supply of floor protection, WHS compliance, and site establishment for a live school environment.

  • Partition Installation – Construction of solid plasterboard and glazed partitions with aluminium trims, doors, and compliant hardware to AS1428 standards.

  • Ceilings – Installation of new set plasterboard ceilings in office areas, including framing and finishing to Level 4.

  • Electrical & Data – Installation of LED lighting, power points, and dual data points with cabling connected to the existing E block patch panel.

  • Painting – Full painting of new walls, ceilings, and doors with compliant coatings and finishes.

  • Optional Works – Supply and install of acoustic pinboards, glass view panels, privacy film, and commercial-grade carpet tiles if selected by client.

  • Cleaning & Waste – Progress cleaning during works and detailed final clean on completion, including removal of all construction waste.

  • Project Management – Coordination of all trades, subcontractors, and delivery schedules with full client communication throughout.

     