Henty House
Sydney CBD, Central Sydney, NSW

Lobby Fitout project completed by DY Constructions

Project Details

Location

Sydney CBD, Central Sydney, NSW

Industry

Strata Committee

Size

65m2

Value

$300k

Designer

DY Constructions Australia

Delivery Method

Lump Sum

Duration

8 weeks

  • Lift lobby refurbishment
  • After-hours works
  • Live environment foyer upgrade
  • Temporary hoarding
  • Frameless glass sliding doors
  • Internal cladding
  • Digital directory board
  • Mirror cladding
  • LED feature lighting

Project overview

A detailed lobby and common area refurbishment completed in Sydney CBD for The Strata Committee of Henty House — enhancing presentation, attractiveness, value, and amenity through careful planning and quality finishes.

Client Brief

The Strata Committee of Henty House engaged DY Constructions Australia to undertake a comprehensive foyer refurbishment at 379 Kent Street, Sydney CBD.

The project involved a full redesign and fitout of the ground floor lift foyer and entry areas, incorporating new floor tiling, frameless automatic glass sliding doors, vertical timber battens, mirrored finishes, bespoke joinery, and feature lighting. The refurbishment was part of a broader base building upgrade, focused on enhancing functionality and elevating the presentation of this key entry space to improve the visitor experience and support the building’s ongoing asset repositioning.

Challenges

The project required careful management to minimise disruption in a busy CBD location. With the lobby closed during works, foot traffic needed to be redirected safely. After-hours installation of glass, coordination with lift companies, and strict noise management were essential in the strata environment. As the building’s main foyer, attention to detail was critical to meet aesthetic expectations and bring the client’s design vision to life.

 
 
The Solution

DY Constructions carefully planned and coordinated all stages of the building refurbishment to minimise disruption. Regular meetings with stakeholders ensured clear communication and alignment on design and finishes. Noisy and high-impact works, such as glass installation, ceiling bulkheads and feature lighting, were scheduled outside peak hours to meet strata requirements. The team worked closely with specialist trades and lift contractors to deliver detailed elements, including vertical timber battens, bronze mirror finishes and a recessed digital directory display. Ongoing quality control and staged handovers ensured the foyer upgrade met the project’s high design and presentation standards.

The Result

Working closely with the client and design team, DY Constructions delivered a sophisticated lift foyer and entry upgrade that transformed the ground floor at Henty House. Featuring premium finishes such as large format tiles, new automatic glass sliding doors, vertical timber battens, bronze mirrors, and integrated lighting, the refurbished foyer now offers a sleek and inviting space that reflects the building’s repositioning objectives.

The project was completed while maintaining building operations and minimising disruption. Positive feedback from residents and the strata committee led to DY Constructions securing further fitout works within the building. This successful building refurbishment not only improved day-to-day functionality but also enhanced the asset’s value and appeal within Sydney’s competitive CBD market.

Client Review

DY Constructions rebuilt our foyer at 379 Kent Street Sydney in April 2020. We went through a detailed bidding process and obtained quotes from 5 different builders. DY Constructions submitted a highly competitive and detailed proposal. DY Constructions also did in-house plans which saved us money in not having to engage an architect. The project was delivered on time and within budget. A special thank you to their project manager Jason Frawley. He was fantastic and kept me up to date throughout the project. I would highly recommend DY constructions for any building project in Sydney. DY Constructions have definitely earned a 5 star review!

Anthony Warner
Director

Client testimonial from Henty House

Get In Touch

Please Submit Your Enquiry and our friendly staff will contact you to arrange a free consultation at your premises to discuss your project in detail.

Scope of Works

  • Site Preparation: Floor protection, signage, and coordination with building management in a live CBD environment.

  • Demolition & Remedial Works: Removal of outdated ceiling panels, fittings, and damaged finishes; make-good repairs.

  • Ceiling & Lighting: Installation of new ceiling grid and tiles; upgraded LED lighting and associated electrical adjustments.

  • Wall & Floor Finishes: Application of new wall paint, patching, and floor preparation for common area refurbishment.

  • Joinery & Feature Elements: Custom timber batten screening, bronze mirror wall cladding, and digital directory install.

  • Glazing & Entry: Frameless glass sliding doors installed at main entry; access maintained throughout construction.

  • Compliance Upgrades: Lift lobby and entry compliance improvements including tactile indicators and signage.

  • Project Coordination: Staged after-hours works, certifier communication, tenant notifications, and final cleaning.